South Coast Traction has been underway for close on two years and at this stage nothing has been able to complete a circuit on the baseboard.
A lot of work had to be undertaken to get the room ready the major task being the laying of carpet tiles right through the shed. This wasn't a hard project except for the bits under the existing portions of the layout. The baseboard and legs had to raised to get the tiles underneath.
There was plenty of design work to get the track layout worked out. I have tried to make it an interesting design with options of routes and two termini that the cars can operate between, that is also dependent on them being twin pole equipped.
I came to the realisation that distractions on the layout such as doing small pockets of scenery and assembling the multitude of building needed wasn't advancing the trackwork. If you put the projects required the first one would be to get the track laid. It doesn't have to be every piece of track so I will concentrate on getting a circle of track around the baseboard.
What has also given me incentive to get a move on was that I have nominated a gathering of friends here later this year to see what has been done. These have been regular meetings over many years where we gather, have a drink, barbeque, lunch, a layout run (if they have one) maybe a video if we have time and then decide who will have the next one.
So after laying some of the track that only requires ready made points and track, I now realise that I have to get on with doing the hand laid track slog again. I say again as it has been around fifty odd years since I last handlaid points (some of the earlier blogs detail that). The previous layout had the overhead live and return through the rails. This made trackwork so much easier than using the two rail method. Going down this path will mean I will be able to have operation well before the overhead is erected. And also other people who have 2 rail traction will be able to run their equipment on the layout. It will be designed for DCC operation but if I have to switch over to DC then the whole layout will be live as one large section. The depot will be isolated so that any DCC trolleys can be left there saving them from having to being removed from the layout.
Previously I had a go at the first handlaid point but got into trouble when I discovered that the Fast Track sleepers I obtained had different heights from the smaller ones compared with the longer point sleepers. Dumb. So I decided to give it a rest and decided that I would try something simpler in doing some plain points.
I thought the best way to get some consistency in each point was to create a full size template drawing. As previously stated I have set on 11 inch radius to accommodate the Electroliner in the future. I am aware that I could have gone to a smaller radius but this size looks good, not too tight and not too large. I knocked out a right hand point in Coreldraw and then flipped it for a left hand point. The template allows to pre-bending of the rail to the correct radius or as close as possible. By doing this the extra tension that would be there by forcing the rail into the right radius is eliminated. It also allows for a uniform check rail and closure rails length. Win win.
![]() |
11 inch point template
|
The first point I laid used some code 83 rail that I had spare from the old HO layout. The sleepers were removed from the rail. Some of the ready to run track was unfortunately Code 100 which when laid beside the Code 75 looks way bigger. I also managed to get some Peco code 75 rail similarly stripped from the sleepers.
![]() |
| Throw bar and isolating the rails to be done |
The photo above shows the results of the first two points constructed. A little bit on the rough side but the true test will come when the throwbar and the PC boards are cut to enable two rail operation. I will be using some Tortoise point motors to power them but that will be a problem for another day. I have never used this type of point motor so that another thing I will have to study. These points will be ballasted in their own right of way and not street ones. They will be a single blade if I can work out how to make them. There is a continuous radius of 11 inches through the complete point and I was lucky to find an 11 inch radius template originally designed for N scale that fits right between the rails. As you can see in the photo I have also incorporated some of the Peco track sleepers onto the rails between the points. This also acts to keep the track in gauge. To test the track at this stage I use a single bogie and run it through to see if there are any tight spots. And also I use an NMRA track gauge to get the track right.
![]() |
| The grey track template and bogie for track testing |
So far I have managed to get around three points constructed and at this stage seem to be in gauge and OK. I have pushed a tram and bogie freight car the points and there doesn't seem to be any binding. A lot of surplus/extra solder on the sleepers will be removed later on with the copper wick that sucks up the solder.
![]() |
| And my first curved one. |
Well I have bitten the bullet and made the hard start on the handlaid track. I still think I will prefer putting up the overhead than doing the trackwork but the track has to be laid first. Then once the trackwork is done ballasted and looking pretty then the overhead goes up.
![]() |
| Car 250 waits patiently in the depot for the overhead |
This a progress diagram showing what track is currently laid and what there is to go. I will update when more gets done.






















































